Mian Al Fursan
14 May 2026

14 May 2026

80%Overall▲ +7% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in interior finishing and electromechanical systems, with the overall project completion reaching 80%. Current works are focused on ceramic tiling, final plastering, and the installation of suspended ceiling frameworks.
Detected changes
Interior Finishing Works100%

Continuation of floor and wall ceramic tiling in bathrooms and corridors, alongside the commencement of staircase marble installation and the application of putty and primer coats.

Suspended Ceiling Works95%

Installation of metal grids for gypsum ceilings and fixing moisture-resistant gypsum boards in designated areas.

Electromechanical Works90%

Extending electrical wiring within distribution boxes and preparing lighting points and switches, in addition to plumbing and drainage installations in bathrooms.

Progress reading

The visual evidence aligns with the recorded increase in the finishing works category (+17%), showing intensive activity in large-scale tiling. The images also reflect a 12% advancement in electromechanical works, evidenced by the visible wiring extensions and distribution boxes.

vs previous visit

Compared to the previous site visit photos, the project has progressed from the rough plastering and piping installation stage to the actual tiling and gypsum ceiling closure phase, with the emergence of specialized labor for marble installation and painting that was not heavily present during the previous visit.

Expected next milestones

Completion of final painting works, installation of lighting units and sanitary fixtures, and finishing of external boundary walls.

Progress

0%OverallAverage item progress
2/5 completeavg ▲ +7%
Concrete Works
0%
Finishing Works▲ +17%
0%
Masonry
0%
Electromechanical▲ +12%
0%
Fencing▲ +8%
0%