14 May 2026
Main video
Engineering Report
Detected changes
Continuation of floor and wall ceramic tiling in bathrooms and corridors, alongside the commencement of staircase marble installation and the application of putty and primer coats.
Installation of metal grids for gypsum ceilings and fixing moisture-resistant gypsum boards in designated areas.
Extending electrical wiring within distribution boxes and preparing lighting points and switches, in addition to plumbing and drainage installations in bathrooms.
Progress reading
The visual evidence aligns with the recorded increase in the finishing works category (+17%), showing intensive activity in large-scale tiling. The images also reflect a 12% advancement in electromechanical works, evidenced by the visible wiring extensions and distribution boxes.
vs previous visit
Compared to the previous site visit photos, the project has progressed from the rough plastering and piping installation stage to the actual tiling and gypsum ceiling closure phase, with the emergence of specialized labor for marble installation and painting that was not heavily present during the previous visit.
Expected next milestones
Completion of final painting works, installation of lighting units and sanitary fixtures, and finishing of external boundary walls.