15 Feb 2026
Main video
Engineering Report
Detected changes
Completion of exterior painting and installation of windows and doors for the majority of villas, with rooftop water tanks appearing fully installed.
Significant progress in internal road grading, installation of sidewalk curbs, and interlock paving in side walkways.
Ongoing formwork and reinforcement for a central service building (mosque or commercial center) in the heart of the project.
Visible HVAC ducting and outdoor units on rooftops, along with the completed installation of street lighting poles in certain areas.
Progress reading
The images align with the reported completion rates; the progress in mechanical and electrical works (+4% and +3%) is reflected in the intensified installation of rooftop units and lighting poles. The steady finishing rate at 97% indicates a focus on fine interior details that are not clearly visible in aerial photography.
vs previous visit
Compared to the January photos, there is clear progress in the paving of internal roads (initial asphalt) and an increased density of sidewalk tiling completed in front of the villas, in addition to tangible progress in the structure of the central service building.
Expected next milestones
Completion of the final asphalt layer, installation of directional signage, and commencement of inspection and testing procedures for electrical and mechanical systems in preparation for handover.