18 Jan 2026
Main video
Engineering Report
Detected changes
Continuation of concrete pouring using pumps, preparation of reinforcement steel and metal formwork for upper floors and perimeter walls, with completion reaching 98%.
Significant progress in external plastering, stone cladding installation, and the fitting of decorative metal screens (CNC) on windows, in addition to external tiling works.
Final features of internal roads between villas are visible, with ongoing excavation and utility piping, and the installation of rooftop water tanks.
Manual breaking of some concrete elements observed (likely for architectural modifications or honeycombing treatment).
Progress reading
The visual evidence aligns with the reported completion rates; aerial photographs (13-19) reflect the completion of concrete structures for most blocks, while close-up shots (2, 4, 5) show a surge in finishing works, which jumped by 11% to reach 74%.
vs previous visit
Compared to the previous visit, it is noted that the facades of entire rows of villas have been completed with stone cladding and mashrabiyas. Work has transitioned from the structural phase to the final finishing stage across extensive areas, with tangible progress in the construction of perimeter walls.
Expected next milestones
Completion of the remaining concrete pouring (2%), intensification of electrical wiring works to increase the completion rate (67%), and the commencement of final asphalt paving for the walkways.