Mian Villas
18 Jan 2026

18 Jan 2026

84%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The site visit revealed significant progress in the Mayan Villas project, with overall completion reaching 84%. Current efforts are focused on finalizing the concrete structures for the final phases, alongside an accelerated pace for exterior and interior finishes and the installation of mechanical and electrical systems across most units.
Detected changes
Concrete Structure95%

Continuation of concrete pouring using pumps, preparation of reinforcement steel and metal formwork for upper floors and perimeter walls, with completion reaching 98%.

External Facades and Finishes98%

Significant progress in external plastering, stone cladding installation, and the fitting of decorative metal screens (CNC) on windows, in addition to external tiling works.

General Site and Infrastructure90%

Final features of internal roads between villas are visible, with ongoing excavation and utility piping, and the installation of rooftop water tanks.

Demolition and Modification Works85%

Manual breaking of some concrete elements observed (likely for architectural modifications or honeycombing treatment).

Progress reading

The visual evidence aligns with the reported completion rates; aerial photographs (13-19) reflect the completion of concrete structures for most blocks, while close-up shots (2, 4, 5) show a surge in finishing works, which jumped by 11% to reach 74%.

vs previous visit

Compared to the previous visit, it is noted that the facades of entire rows of villas have been completed with stone cladding and mashrabiyas. Work has transitioned from the structural phase to the final finishing stage across extensive areas, with tangible progress in the construction of perimeter walls.

Expected next milestones

Completion of the remaining concrete pouring (2%), intensification of electrical wiring works to increase the completion rate (67%), and the commencement of final asphalt paving for the walkways.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +6%
Concrete Works▲ +2%
0%
Finishing Works▲ +11%
0%
Mechanical Works▲ +4%
0%
Electrical Works▲ +5%
0%
Fencing▲ +10%
0%

3D Visualization

Ground Photography

Drone Imagery