Mian Villas
15 Dec 2025

15 Dec 2025

81%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in the Mayan Villas project, with the overall completion rate reaching 81%. Current efforts are focused on completing the concrete structures for the final phases, alongside the acceleration of exterior and interior finishing works and the installation of mechanical and electrical systems, while work continues on the perimeter walls.
Detected changes
Concrete Structure95%

Ongoing concrete pouring using pumps, preparation of reinforcement steel for columns and slabs in remaining areas, and dismantling of metal formwork in structurally completed villas.

External Facades and Finishes98%

Installation of decorative metal screens (GRC/Metal) on windows, completion of external plastering and painting, and installation of floor tiling in outdoor courtyards.

General Site and Fencing90%

Execution of excavation and leveling for internal pathways between villas, continued construction and pouring of external fence columns, and preparation of underground utilities.

Mechanical and Electrical Works85%

Installation of rooftop water tanks, extension of sewage and water supply networks, and preparation of electrical cable conduits.

Progress reading

The visual evidence aligns with the slight (1%) increase across all items; aerial photographs show vast areas transitioning from the structural shell stage to the plastering and painting stage, supporting the progress of finishes to 63%. Furthermore, the presence of tanks and pumps confirms the advancement of mechanical and electrical works.

vs previous visit

Compared to the previous visit photos, it is noted that the installation of mashrabiyas has been completed in a larger number of villas, scaffolding has been removed from additional facades, and there is significant progress in soil leveling for the general site compared to the previous state which showed irregular sand accumulations.

Expected next milestones

Completion of the remaining concrete pouring to reach 100%, commencement of asphalt works for internal pathways, and intensification of interior painting works.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +1%
Concrete Works▲ +1%
0%
Finishing Works▲ +1%
0%
Mechanical Works▲ +1%
0%
Electrical Works▲ +1%
0%
Fencing▲ +1%
0%