15 Dec 2025
Main video
Engineering Report
Detected changes
Ongoing concrete pouring using pumps, preparation of reinforcement steel for columns and slabs in remaining areas, and dismantling of metal formwork in structurally completed villas.
Installation of decorative metal screens (GRC/Metal) on windows, completion of external plastering and painting, and installation of floor tiling in outdoor courtyards.
Execution of excavation and leveling for internal pathways between villas, continued construction and pouring of external fence columns, and preparation of underground utilities.
Installation of rooftop water tanks, extension of sewage and water supply networks, and preparation of electrical cable conduits.
Progress reading
The visual evidence aligns with the slight (1%) increase across all items; aerial photographs show vast areas transitioning from the structural shell stage to the plastering and painting stage, supporting the progress of finishes to 63%. Furthermore, the presence of tanks and pumps confirms the advancement of mechanical and electrical works.
vs previous visit
Compared to the previous visit photos, it is noted that the installation of mashrabiyas has been completed in a larger number of villas, scaffolding has been removed from additional facades, and there is significant progress in soil leveling for the general site compared to the previous state which showed irregular sand accumulations.
Expected next milestones
Completion of the remaining concrete pouring to reach 100%, commencement of asphalt works for internal pathways, and intensification of interior painting works.