22 Apr 2026
Main video
Engineering Report
Detected changes
Completion of exterior plastering and painting (profile), installation of main doors and automatic garage doors, along with the installation of exterior wall lighting units.
Installation of floor tiling and suspended ceilings (gypsum), along with lighting fixtures (chandeliers) in some villas, and the installation of iron and glass railings for staircases.
Installation of sanitary ware (toilets and washbasins) in bathrooms, and installation of electrical switches and main panels, with ongoing final wiring works.
Significant progress in paving exterior walkways and courtyard tiling, with the project's urban fabric appearing complete in aerial photographs.
Progress reading
The visual evidence aligns with the reported completion rates; the quality of the final finishes reflects the high progress in mechanical works (87%) and finishing (84%). The increase in electrical work (+3%) is clearly visible in the installation of lighting units and switches.
vs previous visit
Compared to the previous visit, work has progressed from the internal infrastructure stage to the final installation of sanitary fixtures and lighting units, with facade painting now completed for a larger number of residential units.
Expected next milestones
Completion of final electrical installations, testing of mechanical systems, final site cleaning, and commencement of preliminary handover procedures.