15 Feb 2026
Main video
Engineering Report
Detected changes
Completion of exterior plastering, profile painting, and installation of decorative metal screens for windows across most villas.
Progress in asphalt paving for internal roads, installation of curbstone, and interlocking tiles for pedestrian walkways.
Ongoing formwork and reinforcement steel works for a central building (mosque or service facility) at the heart of the project.
Installation of overhead water tanks and piping extensions on the roofs of completed villas.
Progress reading
The visual progress aligns with the reported completion rates; the images reflect that finishing works have reached 80%, evidenced by the completion of entire block facades. The increase in the fencing category (+5%) is visible in the completion of front villa walls and the installation of gates.
vs previous visit
Compared to the previous visit, the project has progressed from the structural and plastering stages in several sectors to the final painting phase and the installation of rooftop mechanical systems, with a clear improvement in general site organization and street paving.
Expected next milestones
Completion of street lighting, finishing landscape works, and commencing final inspection procedures for electrical and mechanical systems.