11 Nov 2025
Main video
Engineering Report
Detected changes
Completion of concrete structures for most villas on-site, with ongoing carpentry and reinforced steel work for remaining structural elements in specific areas.
Execution of external plastering and final paint finishes (sprays), along with the installation of decorative metal screens on windows and facades for a large number of units.
Ongoing internal road grading and soil leveling, with construction material stockpiles and heavy machinery (graders) working on leveling the pathways.
Installation of upper water tanks on the roofs of structurally completed villas.
Progress reading
Aerial and ground photography show that the project has largely moved past the foundation and structural framing stages in most sectors. Work has transitioned to the exterior finishing and site landscaping phase, reflecting actual progress that exceeds the zero percent completion rate recorded in the initial report.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of paving and lighting for the general site, commencement of interior finishing works, and installation of final mechanical and electrical systems.