Mian Villas
11 Nov 2025

11 Nov 2025

79%Overall-14% · vs previous visit

Main video

Engineering Report

A field visit to the Mayan Villas project was conducted on November 11, 2025, where significant progress was observed in the concrete structures and exterior finishing works for a large number of units. The project is in advanced stages of external construction, with ongoing earthwork and leveling for the general site.
Detected changes
Concrete Structure95%

Completion of concrete structures for most villas on-site, with ongoing carpentry and reinforced steel work for remaining structural elements in specific areas.

External Facades90%

Execution of external plastering and final paint finishes (sprays), along with the installation of decorative metal screens on windows and facades for a large number of units.

General Site85%

Ongoing internal road grading and soil leveling, with construction material stockpiles and heavy machinery (graders) working on leveling the pathways.

Roofs and Annexes95%

Installation of upper water tanks on the roofs of structurally completed villas.

Progress reading

Aerial and ground photography show that the project has largely moved past the foundation and structural framing stages in most sectors. Work has transitioned to the exterior finishing and site landscaping phase, reflecting actual progress that exceeds the zero percent completion rate recorded in the initial report.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of paving and lighting for the general site, commencement of interior finishing works, and installation of final mechanical and electrical systems.

Progress

0%OverallAverage item progress
0/5 completeavg ▼ -20%
Concrete Works-5%
0%
Finishing Works-26%
0%
Mechanical Works-17%
0%
Electrical Works-24%
0%
Fencing-26%
0%