8 Nov 2025
Main video
Engineering Report
Detected changes
Ongoing exterior painting (profile) and installation of decorative wood/metal elements on windows and main facades.
Installation of floor tiling and marble stairs, fitting of glass stair railings, completion of wall painting, and installation of lighting units (chandeliers).
Installation of circuit breakers in main panels, wiring connections, and fitting of final switches and sockets.
Installation of marble washbasins, mixers, and bathroom fixtures, with ongoing insulation and final installation works.
Completion of exterior entrance tiling and installation of outdoor wall lighting units, with final cleaning works remaining.
Progress reading
Visual observations align with the reported completion rates; the 88% progress in finishing is evident in the completion of most painting and flooring works. The 85% completion in electrical works and 90% in mechanical works are clearly visible through the installation of final sanitary ware and electrical fixtures. The concrete structure is fully completed at 100%.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of final site cleaning, operational testing of electrical and mechanical systems, and commencement of preliminary handover procedures.