Mian Villas
8 Nov 2025

8 Nov 2025

93%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The Mayan Villas project was visited on November 8, 2025, with an overall completion rate of 93%. The project is in its final stages of interior and exterior finishing, with ongoing installation of electrical and plumbing fixtures, flooring, and exterior facade painting.
Detected changes
Exterior Facades95%

Ongoing exterior painting (profile) and installation of decorative wood/metal elements on windows and main facades.

Interior Finishes98%

Installation of floor tiling and marble stairs, fitting of glass stair railings, completion of wall painting, and installation of lighting units (chandeliers).

Electrical Works95%

Installation of circuit breakers in main panels, wiring connections, and fitting of final switches and sockets.

Mechanical and Plumbing Works92%

Installation of marble washbasins, mixers, and bathroom fixtures, with ongoing insulation and final installation works.

General Site and Fencing90%

Completion of exterior entrance tiling and installation of outdoor wall lighting units, with final cleaning works remaining.

Progress reading

Visual observations align with the reported completion rates; the 88% progress in finishing is evident in the completion of most painting and flooring works. The 85% completion in electrical works and 90% in mechanical works are clearly visible through the installation of final sanitary ware and electrical fixtures. The concrete structure is fully completed at 100%.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of final site cleaning, operational testing of electrical and mechanical systems, and commencement of preliminary handover procedures.

Progress

0%OverallAverage item progress
1/5 complete
Concrete Worksnew
0%
Finishing Worksnew
0%
Mechanical Worksnew
0%
Electrical Worksnew
0%
Fencingnew
0%