Mian Heights
17 May 2026

17 May 2026

8%Overall▲ +1% · vs previous visit

Engineering Report

Significant progress has been observed in the structural framework of the Mian Heights project, with work focusing on completing the casting of concrete slabs and walls for the villa clusters. External plastering and primary painting have commenced on the show villa, alongside the ongoing mechanical and electrical rough-ins.
Detected changes
Concrete Structure95%

Completion of concrete pouring for slabs and walls across several blocks, with formwork and reinforcement visible in new expansion areas.

Finishes and Facades98%

Execution of external plastering, profile painting, and installation of decorative wooden elements on the show villa facade.

General Site and Infrastructure90%

Ongoing excavation and earth leveling for internal roads, with installation of drainage or water supply networks observed in certain paths.

Progress reading

The images align with the recorded increase in concrete work (+2%), clearly showing the casting of new slabs. Furthermore, the completion of the show villa's facade explains the slight rise in finishing works to 2%.

vs previous visit

Compared to the previous site visit photos, the project has progressed from the foundation and ground floor column stage in the peripheral blocks to the casting of the first-floor slabs. Additionally, the show villa now features complete exterior finishes, whereas it was previously only a concrete shell.

Expected next milestones

Completion of the roof slab casting for the upper annexes in the current blocks, and the commencement of masonry work (blockwork) for internal partitions.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +1%
Concrete Works▲ +2%
0%
Finishing Works▲ +1%
0%
Mechanical Works
0%
Electrical Works▲ +1%
0%
Fencing
0%