15 Mar 2026
Main video
Engineering Report
Detected changes
Ongoing installation of floor tiles, interior plastering, and suspended ceiling (gypsum board) installation, along with the commencement of putty and primer painting works.
Execution of exterior plastering for facades and completion of aesthetic element installations and exterior painting for select units.
Wiring of electrical cables within main and sub-panels, and preparation of lighting points and switches.
Ongoing leveling of surrounding grounds, trenching for utility extensions, and construction of exterior boundary walls for the units.
Progress reading
The visual documentation aligns with the recorded increase in the finishing works category (+8%), showing extensive activity in tiling and painting. Furthermore, the progress in electromechanical works (+4%) reflects the start of internal network installations.
vs previous visit
Compared to the previous visit, the project has progressed from the structural and masonry stage to the advanced finishing stage. Gypsum ceilings and painting works are now visible in the current photos, which were incomplete previously, alongside clear progress in the development of the general site layout.
Expected next milestones
Completion of final painting works, installation of sanitary and electrical fixtures, and commencement of external paving and landscaping works.