26 Apr 2026
Main video
Engineering Report
Detected changes
Completion of the current floor column casting and commencement of formwork and reinforcement for the new floor slab, with the stationary concrete pump visible on-site.
Continuation of wall construction using concrete blocks on the lower floors (first and second), with architectural openings clearly visible.
Organization of the material storage area (reinforcement steel and timber) in the front yard, with the tower crane continuing to transport materials to the upper floors.
Progress reading
The visual evidence aligns with the overall completion rate (27%), as the structural framework has passed the halfway mark (56%), and masonry and initial finishing works have commenced at (5%). The most significant change is the transition from the foundation and basement stages to the construction of the typical floors.
vs previous visit
Compared to the previous (nighttime) visit photos, the work has progressed from column formwork and slab preparation to the completion of an additional floor structure and the commencement of masonry works that were not previously visible, confirming the recorded 56% achievement jump for the structural phase.
Expected next milestones
Casting the current floor slab, completing masonry works for the remaining floors, and commencing the rough-in for mechanical, electrical, and plumbing (MEP) works.