18 Jun 2026
Main video
Engineering Report
Detected changes
Continuation of formwork and reinforcement for the final floor roof, with new concrete columns and fixtures currently under construction using a concrete pump and tower crane.
Clear progress in closing external and internal voids using red clay and cement blocks, with works reaching advanced stages on the typical floors.
Commencement of electrical and plumbing installations within the floors where masonry is complete, accounting for the increase in finishing progress to 8%.
Organization of the staging area and heavy equipment presence (tower crane and concrete pump) alongside ongoing reinforcement works in the external yards.
Progress reading
The site photos align with the recorded increase in concrete work (+8%), showing active construction on the upper slabs. Furthermore, the photos support the rise in finishing works (+2%) through the progress of masonry and internal installations visible on the middle floors.
vs previous visit
Compared to the previous visit's photos, we observe the completion of at least two additional roof slabs, a significant increase in the density of masonry work which was largely absent previously, and the tower crane has moved to operate at higher levels.
Expected next milestones
Completion of the final floor roof slab (Structure Top-out), and the intensification of internal plastering and electromechanical installations.