22 Apr 2026
Main video
Engineering Report
Detected changes
Completion of exterior painting (profile), installation of main doors and automatic garage doors, along with the final installation of outdoor lighting units and meter boxes.
Completion of flooring (porcelain), wall painting, and installation of gypsum ceilings with lighting units (chandeliers and spotlights), as well as the installation of interior wooden doors.
Installation of electrical outlets and switches, completion of sanitary ware fixtures (sinks, toilets) and mixers, and installation of exhaust fans in kitchens and bathrooms.
Completion of internal road paving for the project, landscaping of walkways, and the appearance of all residential blocks in their final state ready for handover.
Progress reading
The visual evidence aligns with the recorded completion rate (100%), as there are no ongoing construction or finishing works, and all elements visible in the images reflect a state of full readiness.
vs previous visit
Compared to the previous visit, it was confirmed that all minor finishing snags have been resolved, and the installation of electrical and mechanical accessories—which were in their final stages—has been completed, resulting in the stabilization of completion rates at their maximum level.
Expected next milestones
Commencement of final handover procedures to owners and the activation of maintenance and security services for the general site.