8 Nov 2025
Main video
Engineering Report
Detected changes
Completion of the structural framework for most residential units, along with the finishing of external wall construction and boundary fences.
Execution of external plastering and texture painting (profile) at varying stages, including the installation of rooftop water tanks.
Observation of wooden door frame installations and the fitting of lighting fixtures (chandeliers) in some completed units.
Presence of excavation and lifting equipment (excavators, loaders, telehandlers) performing earthwork leveling and material transport between villas.
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates that the project has reached the final stages of structural and facade work. This discrepancy exists because this visit serves as the project baseline.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of internal street paving, finishing the remaining facade painting, and commencing the installation of doors and windows.