19 Jan 2026
Main video
Engineering Report
Detected changes
Completion of the structural framework for the majority of residential units, with a central service or administrative building currently under construction at the roof casting and formwork preparation stage.
Completion of plastering and external painting for most villas, installation of glass windows and external doors, and the appearance of wall-mounted lighting fixtures.
Installation of overhead water tanks on villa roofs, ongoing installation of electrical switches and external lighting, and the fitting of air conditioning units.
Progress in paving internal roads with asphalt and installing interlock for sidewalks, along with the completion of villa boundary walls and automated garage gates.
Progress reading
The images align with the reported completion rates; the finished facades and boundary walls reflect the 86% completion in finishing works and 94% in fencing. The stability of percentages compared to the previous visit indicates a focus on fine interior details or general site works that did not result in a major jump in overall percentages.
vs previous visit
Compared to previous images, there is clear progress in the leveling of internal roads and the commencement of final paving works, alongside an increase in the number of units with completed facade installations.
Expected next milestones
Completion of the final asphalt layer paving, finishing the installation of street lighting, and initiating inspection and testing procedures for mechanical and electrical systems.