Suhail Garden
16 May 2026

16 May 2026

100%OverallFirst visit — no previous comparison.

Main video

Engineering Report

All construction and finishing works for the Suhail Garden project have been completed, reaching a total completion rate of 100%. The images show the completion of concrete structures, external facades, paving works, and full site preparation, with some final fit-out works ongoing for the mosque and service facilities.
Detected changes
Concrete Structure and Masonry100%

Completion of all concrete structures for the villas and the mosque, with scaffolding remaining around the mosque minaret for final finishing works.

External Facades and Finishes100%

Completion of external facade painting for the villas, along with the installation of windows, main doors, and automatic garage doors.

General Site and Fencing100%

Completion of asphalt paving for internal roads, installation of interlock for sidewalks and walkways, and completion of villa boundary walls.

Progress reading

The visual evidence aligns with the reported completion rate (100%), as the villas appear fully ready for occupancy. A minor observation is noted in the mosque area, which is currently undergoing cleaning and final touches.

vs previous visit

Compared to the previous visit, paving works have been completed in areas that were previously unpaved, most construction debris has been cleared from the villa perimeters, and all external fixtures (doors, lighting) have been fully installed.

Expected next milestones

Removal of remaining scaffolding from the mosque, final cleaning of the general site, and commencement of final handover procedures.

Progress

0%OverallAverage item progress
5/5 complete
Concrete Works
0%
Finishing Works
0%
Mechanical Works
0%
Electrical Works
0%
Fencing
0%