16 May 2026
Main video
Engineering Report
Detected changes
Completion of all concrete structures for the villas and the mosque, with scaffolding remaining around the mosque minaret for final finishing works.
Completion of external facade painting for the villas, along with the installation of windows, main doors, and automatic garage doors.
Completion of asphalt paving for internal roads, installation of interlock for sidewalks and walkways, and completion of villa boundary walls.
Progress reading
The visual evidence aligns with the reported completion rate (100%), as the villas appear fully ready for occupancy. A minor observation is noted in the mosque area, which is currently undergoing cleaning and final touches.
vs previous visit
Compared to the previous visit, paving works have been completed in areas that were previously unpaved, most construction debris has been cleared from the villa perimeters, and all external fixtures (doors, lighting) have been fully installed.
Expected next milestones
Removal of remaining scaffolding from the mosque, final cleaning of the general site, and commencement of final handover procedures.