12 Mar 2026
Main video
Engineering Report
Detected changes
100% completion of all concrete structures for residential villas and service buildings, including the sealing of all architectural openings.
Completion of external painting and cladding, installation of windows and external doors, and installation of rooftop water tanks for all units.
Completion of internal road asphalt paving, installation of interlocking sidewalk tiles, and finishing of villa perimeter walls and private gates.
Visible installation of water tanks and external fixtures, with completion of external lighting wiring and street light poles across the general site.
Progress reading
The visual evidence aligns with the reported completion rates, as finishing works progressed from 97% to 100%. This is evident in the completion of fine facade details and final paving works that were underway during the previous visit.
vs previous visit
Compared to the previous site visit photos, we observe the removal of heavy construction equipment from the villa surroundings, the completion of the final asphalt layers and sidewalk marking, and the finishing of remaining paintwork in certain areas.
Expected next milestones
Commencement of final unit handover procedures, activation of permanent electrical power, and final site cleaning works.