Mian Villas
25 Mar 2026

25 Mar 2026

88%Overall▲ +1% · vs previous visit

Main video

Engineering Report

Site visit report for the Mayan Villas project dated March 25, 2026, showing an overall completion rate of 88%. Current works are focused on final finishing stages, MEP (mechanical, electrical, and plumbing) installations, and the completion of boundary walls, with the concrete structure for the entire project reaching 100% completion.
Detected changes
Concrete Structure and Masonry100%

Completion of all concrete works for the main buildings, with ongoing internal partition masonry and perimeter wall construction for the remaining units.

External Facades and Finishes95%

Significant progress in external plastering and base coat painting, along with the installation of overhead water tanks for all structurally completed villas.

Insulation and Roofing Works90%

Execution of waterproofing and thermal insulation for roofs using bitumen membranes, followed by rigorous testing.

Electrical and Mechanical Works85%

Installation of cable conduits and internal distribution boxes, along with the extension of overhead supply networks connected to the tanks.

Progress reading

Visual evidence aligns with the reported completion rates; the structural completion (100%) is clearly visible in aerial shots, while field footage reflects the progress of finishing works (83%) and insulation. The increase in the boundary walls segment (+4%) is evident in the completion of partition walls between the villas.

vs previous visit

Compared to the February visit, the project has progressed from the open-structure phase to the intensive finishing stage; most rooftop water tanks have been installed, and paving and leveling works for internal roads have commenced, which were not evident during the previous visit.

Expected next milestones

Completion of final exterior facade painting, installation of lighting units, and commencement of final asphalt works for the general site.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +2%
Concrete Works▲ +1%
0%
Finishing Works▲ +3%
0%
Mechanical Works▲ +1%
0%
Electrical Works▲ +1%
0%
Fencing▲ +4%
0%

3D Visualization

Ground Photography

Drone Imagery

ShareChat on WhatsApp