Mian Villas
17 Jun 2026

17 Jun 2026

97%Overall▲ +7% · vs previous visit

Main video

Engineering Report

The Mayan Villas project has reached very advanced stages with an overall completion rate of 97%. Concrete structures are 100% complete, with significant progress in final finishes, exterior facades, and general site work, indicating that unit handover is imminent.
Detected changes
Exterior Facades and Finishes95%

Completion of exterior painting (profile), installation of metal frames, windows, and main doors for most villas, with architectural final touches clearly visible.

General Site and Perimeter Walls90%

Significant progress in asphalt paving of internal roads and installation of interlocking tiles within villa courtyards, along with the completion of perimeter wall construction, painting, and garage gate installation.

Roofing and Mechanical Works85%

Installation of upper water tanks on villa roofs and extension of visible HVAC and drainage networks, reflecting a major leap in mechanical completion rates.

Electrical Installations100%

Installation of external meter boxes and wall-mounted lighting units on perimeter walls and facades, explaining the substantial increase in electrical completion (+20%).

Progress reading

The visual updates align with the significant increase in completion rates, particularly in the electrical works which jumped from 72% to 92%, evidenced by the completion of external wiring. Furthermore, the 94% progress in finishing works is visually supported by the removal of scaffolding and the completion of facade painting across most project sectors.

vs previous visit

Compared to the April visit, the project has progressed from the 'active construction' phase to the 'final finishing' stage; streets that were previously unpaved have now been asphalted, boundary walls that were under construction are complete, and the units have reached their final, move-in-ready form.

Expected next milestones

Completion of operational testing for electricity and water systems, finishing of landscaping and final site coordination, and the commencement of preliminary handover procedures.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +10%
Concrete Works
0%
Finishing Works▲ +10%
0%
Mechanical Works▲ +9%
0%
Electrical Works▲ +20%
0%
Fencing▲ +9%
0%