17 Jun 2026
Main video
Engineering Report
Detected changes
Completion of exterior painting (profile), installation of metal frames, windows, and main doors for most villas, with architectural final touches clearly visible.
Significant progress in asphalt paving of internal roads and installation of interlocking tiles within villa courtyards, along with the completion of perimeter wall construction, painting, and garage gate installation.
Installation of upper water tanks on villa roofs and extension of visible HVAC and drainage networks, reflecting a major leap in mechanical completion rates.
Installation of external meter boxes and wall-mounted lighting units on perimeter walls and facades, explaining the substantial increase in electrical completion (+20%).
Progress reading
The visual updates align with the significant increase in completion rates, particularly in the electrical works which jumped from 72% to 92%, evidenced by the completion of external wiring. Furthermore, the 94% progress in finishing works is visually supported by the removal of scaffolding and the completion of facade painting across most project sectors.
vs previous visit
Compared to the April visit, the project has progressed from the 'active construction' phase to the 'final finishing' stage; streets that were previously unpaved have now been asphalted, boundary walls that were under construction are complete, and the units have reached their final, move-in-ready form.
Expected next milestones
Completion of operational testing for electricity and water systems, finishing of landscaping and final site coordination, and the commencement of preliminary handover procedures.