Mian Heights
27 Apr 2026

27 Apr 2026

7%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A site visit to the Mian Heights project was conducted on April 27, 2026, showing an overall completion rate of 6%. Current work is focused on the concrete structure stages for several residential units, alongside the commencement of initial rough-ins for mechanical and electrical systems, while general site works remain in the preliminary leveling and grading phases.
Detected changes
Concrete Structure95%

Completion of concrete wall and column casting for the ground and first floors in specific villa clusters, utilizing tunnel formwork systems in the execution.

MEP Works90%

Installation of PVC piping conduits within the concrete structures as preliminary rough-in works synchronized with wall casting.

Site Works and Infrastructure85%

Execution of excavation and earth leveling for internal road networks, along with marking foundation locations for future blocks.

Progress reading

Visual observations align with the concrete completion rate (9%), as several residential blocks appear in advanced stages of the structural framework. The mechanical and electrical percentages (4%) reflect initial installations embedded within the slabs, while the absence of finishing works (0%) is consistent with the project's current status in the structural shell stage.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of roof slab casting for upper floors, commencement of waterproofing works, and intensification of infrastructure network installations for the general site.

Progress

0%OverallAverage item progress
0/5 complete
Concrete Worksnew
0%
Finishing Worksnew
0%
Mechanical Worksnew
0%
Electrical Worksnew
0%
Fencingnew
0%