Mian Al Fursan
17 Feb 2026

17 Feb 2026

65%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in the Mian Al Fursan project, with the overall completion rate reaching 65%. Current efforts are heavily focused on finalizing the remaining concrete structures, which are 99% complete, alongside an acceleration in external plastering and internal finishing works. Additionally, infrastructure and electromechanical installation works are ongoing.
Detected changes
Exterior Facades and Finishes95%

Continuation of exterior plastering works (base coat and leveling) on villa facades, with workers executing tasks using metal scaffolding.

Interior Finishes90%

Commencement of suspended ceiling installation (gypsum board) in select units, along with interior wall plastering works.

Site Works and Infrastructure95%

Execution of excavation and utility line installation (electromechanical) across the project's internal streets using heavy machinery.

Concrete Structure and Masonry98%

Completion of most concrete structures and masonry for the main blocks, with final finishing works underway for the perimeter walls.

Progress reading

The visual evidence aligns with the reported completion rates; aerial photography clearly shows the completion of the concrete structures and masonry (99-100%), while close-up shots reflect the commencement of the finishing phase (25%) through plastering and ceiling works. Furthermore, ongoing excavation works account for the increase in electromechanical progress to 35%.

vs previous visit

Compared to the previous visit, progress is noted in the application of exterior plastering across additional blocks, an increase in the number of units where suspended ceiling works have commenced, and an expanded scope of excavation for utilities across the general site.

Expected next milestones

Completion of exterior plastering for all villas, commencement of primary painting works, and installation of internal mechanical and electrical systems.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +2%
Concrete Works▲ +1%
0%
Finishing Works▲ +4%
0%
Buildings
0%
Electromechanical▲ +2%
0%
Fencing▲ +2%