17 Feb 2026
Main video
Engineering Report
Detected changes
Continuation of exterior plastering works (base coat and leveling) on villa facades, with workers executing tasks using metal scaffolding.
Commencement of suspended ceiling installation (gypsum board) in select units, along with interior wall plastering works.
Execution of excavation and utility line installation (electromechanical) across the project's internal streets using heavy machinery.
Completion of most concrete structures and masonry for the main blocks, with final finishing works underway for the perimeter walls.
Progress reading
The visual evidence aligns with the reported completion rates; aerial photography clearly shows the completion of the concrete structures and masonry (99-100%), while close-up shots reflect the commencement of the finishing phase (25%) through plastering and ceiling works. Furthermore, ongoing excavation works account for the increase in electromechanical progress to 35%.
vs previous visit
Compared to the previous visit, progress is noted in the application of exterior plastering across additional blocks, an increase in the number of units where suspended ceiling works have commenced, and an expanded scope of excavation for utilities across the general site.
Expected next milestones
Completion of exterior plastering for all villas, commencement of primary painting works, and installation of internal mechanical and electrical systems.