20 Apr 2026
Main video
Engineering Report
Detected changes
Continuation of floor tiling and gypsum ceiling installations, with the commencement of wall putty and primer painting works.
Execution of exterior plastering (splatter dash and leveling) for several villas, following the full completion of the concrete structure and masonry.
Installation of electrical distribution boards and wire pulling through conduits, in addition to rough-in plumbing works in the bathrooms.
Progress in the construction of perimeter walls and the commencement of ground leveling around the villas.
Progress reading
The visual documentation aligns with the surge in finishing works (+14%), showing intensive activity in ceramic and gypsum installations. The images also reflect the 100% completion of the concrete structure and masonry, while work continues on electrical systems, which recorded a slight progress of 3%.
vs previous visit
Compared to the previous visit, the project has progressed from the structural and initial perimeter wall stage to the advanced finishing stage; gypsum ceilings and flooring are clearly visible in the current visit, whereas previous photos focused on the structural framework.
Expected next milestones
Completion of final painting works, installation of lighting units and sanitary fixtures, and finishing external plastering while commencing facade painting.