11 Dec 2025
Main video
Engineering Report
Detected changes
Continuation of supplementary roof slab casting for certain units using concrete pumps, with the main structures completed for most villas.
Completion of exterior and interior wall construction using cement blocks for all units visible in the aerial photos.
Commencement of external plastering (spritz coat) and installation of metal mesh, with white facade painting underway for some advanced models.
Observation of marble installation for internal staircases and interior plastering works for rooms.
Ongoing construction of external villa fences and preparation of inter-passageways, with heavy machinery (loaders) present for soil leveling.
Progress reading
The visual documentation aligns with the reported completion rates; aerial photos reflect that building structures are 100% complete and concrete works have reached their final stages (97%). The commencement of the finishing phase (14%) is evident through facade work, painting, and internal staircases, while perimeter walls are in the intermediate stages (55%) as scheduled.
vs previous visit
Compared to the previous visit, we observe a transition from the structural shell phase to the finishing stage; white-painted facades have begun to appear across several blocks, alongside a clear increase in the number of structurally completed perimeter walls.
Expected next milestones
Intensification of internal and external plastering works, commencement of final electromechanical installations, and completion of concrete pouring for the remaining sections of the perimeter walls.