11 Dec 2025

11 Dec 2025

59%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The site visit report for the Mian Al-Fursan project dated December 11, 2025, shows significant progress in exterior and interior finishing works, with structural building works 100% complete. Intensive activity was observed in supplementary concrete pouring, plastering, and exterior painting for several villas, alongside ongoing work on perimeter walls and general site preparation.
Detected changes
Concrete Structure95%

Continuation of supplementary roof slab casting for certain units using concrete pumps, with the main structures completed for most villas.

Masonry Works100%

Completion of exterior and interior wall construction using cement blocks for all units visible in the aerial photos.

Finishes and Facades90%

Commencement of external plastering (spritz coat) and installation of metal mesh, with white facade painting underway for some advanced models.

Interior Finishes85%

Observation of marble installation for internal staircases and interior plastering works for rooms.

General Site and Fencing90%

Ongoing construction of external villa fences and preparation of inter-passageways, with heavy machinery (loaders) present for soil leveling.

Progress reading

The visual documentation aligns with the reported completion rates; aerial photos reflect that building structures are 100% complete and concrete works have reached their final stages (97%). The commencement of the finishing phase (14%) is evident through facade work, painting, and internal staircases, while perimeter walls are in the intermediate stages (55%) as scheduled.

vs previous visit

Compared to the previous visit, we observe a transition from the structural shell phase to the finishing stage; white-painted facades have begun to appear across several blocks, alongside a clear increase in the number of structurally completed perimeter walls.

Expected next milestones

Intensification of internal and external plastering works, commencement of final electromechanical installations, and completion of concrete pouring for the remaining sections of the perimeter walls.

Progress

0%OverallAverage item progress
1/5 complete
Concrete Worksnew
0%
Finishing Worksnew
0%
Masonrynew
0%
Electromechanicalnew
0%
Fencingnew
0%

3D View

Ground Photography

360 View

Drone Shots