Mian Al Fursan
13 Nov 2025

13 Nov 2025

56%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A field visit to the Mian Al Fursan project was conducted on November 13, 2025. The photographs demonstrate significant progress in the structural and masonry work for a large number of villas. The status of the units ranges from roof slab casting and completion of the concrete skeleton to advanced stages of cement block wall construction, with external plastering work commencing on some units.
Detected changes
Concrete Structure95%

Ongoing concrete slab pouring using pumps, with columns and slabs completed for a significant number of residential blocks.

Masonry Works95%

Execution of internal and external cement brick walls, noting the initial electrical and mechanical rough-ins within the walls.

External Facades90%

Commencement of external plastering works for some villas, and installation of metal scaffolding for exterior finishing works.

General Site85%

Heavy equipment presence (bulldozers, concrete pumps, mixers) with ongoing earth leveling and infrastructure preparation between blocks.

التمديدات والخدمات80%

ظهور التأسيسات الأولية للتمديدات الكهربائية والصحية داخل الجدران (أعمال التكسير والتركيب الأولي).

Progress reading

Although the officially recorded completion rate is 0%, the visual evidence indicates substantial progress in structural and masonry works. This discrepancy is likely due to the fact that payment certificates for the executed items have not yet been approved. The project is currently in a very active construction phase.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of masonry work for all units, commencement of internal plastering, and intensification of electromechanical installations.

Progress

0%OverallAverage item progress
0/5 complete
new
0%
new
0%
new
0%
new
0%
new
0%

3D Tour

Ground Photography

360° View

Drone Imagery

ShareChat on WhatsApp