13 Nov 2025
Main video
Engineering Report
Detected changes
Ongoing concrete slab pouring using pumps, with columns and slabs completed for a significant number of residential blocks.
Execution of internal and external cement brick walls, noting the initial electrical and mechanical rough-ins within the walls.
Commencement of external plastering works for some villas, and installation of metal scaffolding for exterior finishing works.
Heavy equipment presence (bulldozers, concrete pumps, mixers) with ongoing earth leveling and infrastructure preparation between blocks.
ظهور التأسيسات الأولية للتمديدات الكهربائية والصحية داخل الجدران (أعمال التكسير والتركيب الأولي).
Progress reading
Although the officially recorded completion rate is 0%, the visual evidence indicates substantial progress in structural and masonry works. This discrepancy is likely due to the fact that payment certificates for the executed items have not yet been approved. The project is currently in a very active construction phase.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of masonry work for all units, commencement of internal plastering, and intensification of electromechanical installations.