30 Jun 2026
Main video
Engineering Report
Detected changes
Ongoing installation of floor and wall tiles in residential units, along with initial painting works and the installation of suspended ceiling frameworks.
Progress in exterior plastering and the installation of stone cladding or final spray finishes for some villas, with scaffolding visible in active work zones.
Completion of perimeter fencing for residential units and installation of overhead water tanks, while earthwork leveling for internal roads continues.
All structural and masonry works for the visible blocks are complete, with units appearing in an advanced stage of finishing.
Progress reading
The visual evidence aligns with the reported completion rates; the increase in finishing works (+5%) is evident through the intensified labor presence within the units (ceramic tiling). Furthermore, the ongoing electrical and plumbing installations shown in the images explain why the electromechanical works remain at 55%.
vs previous visit
Compared to the May visit, we observe a significant number of villas transitioning from the structural shell stage to the plastering and exterior painting stage, in addition to the completion of most front boundary walls that were open during the previous visit.
Expected next milestones
Focusing on finishing electromechanical works (final fixtures), completing exterior facade coatings, and commencing asphalt works for internal roads.