15 Mar 2026

15 Mar 2026

22%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A field visit to the MAKKAH EYE project was conducted on March 15, 2026, where significant progress was observed in the concrete structure and the interior and exterior finishing works for a group of residential units. The site shows intensive activity in carpentry and reinforced steel work for the upper floors, alongside the execution of plastering, painting, and flooring installation in the structurally completed units.
Detected changes
Concrete Structure95%

Continuation of formwork and slab reinforcement for upper floors with an active tower crane on-site, alongside the completion of the concrete structure for several residential villas.

Exterior Facades90%

Execution of exterior plastering works and commencement of the primary painting stages for certain residential units.

Interior Finishes95%

Installation of suspended ceilings (gypsum board), application of putty and interior paints, and wiring of electrical distribution boards.

Flooring and Marble Works95%

Commencement of floor and staircase tiling using cement mortar, ensuring precise leveling with a spirit level.

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates that a major portion of the structural framework has been completed and finishing works have actually commenced. This necessitates an update to the completion percentages to align with the actual progress on the ground.

vs previous visit

No previous visit available for comparison

Expected next milestones

Pouring of reinforced ceilings, completion of exterior painting works, and finishing floor installations for residential units.

Progress

0%OverallAverage item progress
0/2 complete
Concrete Worksnew
0%
Finishing Worksnew
0%