15 Mar 2026
Main video
Engineering Report
Detected changes
Continuation of formwork and slab reinforcement for upper floors with an active tower crane on-site, alongside the completion of the concrete structure for several residential villas.
Execution of exterior plastering works and commencement of the primary painting stages for certain residential units.
Installation of suspended ceilings (gypsum board), application of putty and interior paints, and wiring of electrical distribution boards.
Commencement of floor and staircase tiling using cement mortar, ensuring precise leveling with a spirit level.
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates that a major portion of the structural framework has been completed and finishing works have actually commenced. This necessitates an update to the completion percentages to align with the actual progress on the ground.
vs previous visit
No previous visit available for comparison
Expected next milestones
Pouring of reinforced ceilings, completion of exterior painting works, and finishing floor installations for residential units.