18 May 2026
Main video
Engineering Report
Detected changes
Continuation of steel reinforcement and formwork for upper floor slabs, with electrical and mechanical conduits being installed within the slabs prior to pouring, and concrete pumps stationed on-site.
Execution of internal wall masonry using cement and red bricks across typical floors, with partial completion of internal partitions for corridors and rooms.
Commencement of internal plastering for selected walls, along with the installation of electrical back boxes and plumbing rough-ins within the walls.
Ongoing operation of the tower crane and stockpiling of construction materials in the surrounding areas, while maintaining site organization.
Progress reading
The visual evidence aligns with the reported completion rates; the progress of reinforcement work on the ceilings reflects the 64% completion in concrete works, while the masonry and initial plastering works indicate the start of the 6% progress in the finishing phase.
vs previous visit
Compared to the April 26 visit, there is a notable progress in the height of the concrete structure, along with an increased intensity in internal masonry work and MEP system installations on the floors where formwork has been stripped.
Expected next milestones
Casting the slabs for the current floors, completing masonry work for the remaining levels, and commencing the installation of main mechanical and electrical systems.